Artvin Dam
The Artvin Dam an arch-gravity dam currently under construction on the Çoruh River in Artvin Province, Turkey. Preliminary construction on the dam began in December 2010 and the river diversion tunnels were complete in July 2012 at which time construction on the dam foundation started. The purpose of the dam is hydroelectric power generation and its power station will have an installed capacity of 340 MW when completed. The dam is part of the Çoruh Development Plan and its construction is being supervised by Turkey's State Hydraulic Works. The dam began to impound its reservoir in October 2015 and the power station is expected to be commissioned in 2016. ==See also==
*Yusufeli Dam – under construction upstream *Deriner Dam – downstream